Detected Error in Orifice Design Tool during Operational Support

  • Client:

    International Energy Company
  • Field:

    NCS Flare System

Avoided weeks of lost production by discovering design error before start-up

In brief:

BPT was involved in commissioning of a NCS field. It was performed blowdown of inlet separator with artificial fluids.

By using dynamic blowdown simulations it was identifying missing capacity.

Benefits and key findings:
  • Avoided weeks of lost production by discovering error before “hot” plant (hydrocarbons onboard)
  • Avoided investigation by PSA and lost reputation
  • This project led to BPT-ROX made available to the engineering community